Taiwan's first homemade submarine Haiji is currently conducting Port Port testing. The Taiwan Ship Corporation, which is responsible for manufacturing, revealed that the submarine is expected to be delivered by the ship by November 2025.
Zheng Wenlong, chairman of the Taiwan International Shipbuilding Corporation, revealed in an exclusive interview with the Free Times that the current Haikang's Boang Test (HAT) is roughly carried out in accordance with the plan, but there is no clear at the sea test (SAT) yet a clear one.The timetable.
Zheng Wenlong said that when the Hatsui is conducted by Hat verification tilt test, the left and right angles are less than once."" ".
Zheng Wenlong said that after completing the test of the Port Port, the Haiyu will conduct maritime testing, but the manufacturing team currently does not have a clear timetable because this involves the system safety of the submarine.
He pointed out that the so -called maritime test is to let the Haiyu leave the Taiwan ship to sail at sea. If the Ukkotoma test is fine, the second stage will be performed, including shallow water test vehicles, deep sea trials, and at the same timeTo launch a fake torpedo, if the launch is successful and hit the target ship, it will be successful.
Zheng Wenlong said that the contract delivery date of the Haiyu is November 3, 2025. According to the current progress, as long as all the tests can be completed, the ship should be delivered before the contract period.
The Haiyu warship laid off the water in the Kaohsiung plant of the Taiwan ship on September 28 last year.According to the schedule, the Haiyu was submitted to the Navy for combat evaluation after completing the Port Port test and maritime test in order. The evaluation method includes the launch of the torpedo verification combat system, and finally it can be made into a combat sequence.