The first Taiwanese submarine "Haiji" Haiji ""On Monday (February 26), he left Haichang Factory in the evening and moved into CITIC No. 8 Floating Dock.On the morning of Tuesday (27th) of CITIC, I left the pier in front of the Haichang factory building in the morning, and carried the Haiyu to the small dock of Taiwan Shipbuilding to "sit down" to carry out subsequent equipment installation and test items.

Comprehensive United Daily News and Liberty Times reported that CITIC No. 8 Fuwu Duowu was raised at 7:50 on Tuesday, and a fixed seat was raised, and then many tugboats were taken over or dragged to let CITIC eightThe number was equipped with the Haiyu to leave the dock. After the CITIC No. 8 Floating Dock slowly moved about 100 meters on the sea surface, it stopped and waited for the front cargo wheel to pass the channel, and then opened to the channel.

The Haiji will be installed with batteries, subtramllium and other equipment, and then supplys power by the battery to test the power system, combat system, weapon system, air conditioning and survival system with its own electricity.Select the sea test.

Taiwan media quoted the relevant persons that there was a very important project before the follow -up test, that is, use fresh water to carry out the "washing" procedure for the Haijiao submarine, because the submarine will touch the seawater after going out of the water.There are salt in the outer plate. You must come in to the dock. Before the test, wash water with fresh water, and then continue the follow -up test.

The Haijiao submarine has carried out densely Port Port Test (HAT) a few days ago. It was moved from Haichang Construction Factory to Floatingwood on Monday, and then moved from Floating Dock to the mainway dock of the Taiwan ship.Still part of the HAT project.Relevant sources say that the submarine will move in different deep seas in the future. The overall corrosion prevention work of the hull is important. Therefore, after entering the small dock, the first important action is to "washed".

As for what projects to do in the main dock, the relevant person said that in addition to carrying out the "water washing" procedure first to use fresh water cleaning submarine hulls, the internal project in the dock includes the installation of batteries and installations.Set up masts and subtitrals. Each system continues to be tested in ports. After qualified for standards and acceptance, it will arrange to go to sea for testing.