The Henan Provincial Audit Office announced the fiscal revenue and expenditure audit report last year, and disclosed the audit of the reconstruction reconstruction after the disaster disaster disaster in Henan Province.Including nine counties and a provincial -owned enterprise 405 million yuan (RMB, the same below, the same, 76 million yuan) after the disaster, the reconstruction funds were not compliant; the two county financing platform companies resumed the reconstruction funds of 30.9128 million yuan after the disaster;The city and county falsely reported 22 projects to start or completed, involving a planned investment of 1.283 billion yuan.

According to the Observer Network reported on Saturday (August 5), a report released by the official website of the Henan Provincial Audit Department on July 28 showed that the recovery and reconstruction of the provincial disaster was fully covered and penetrated for two consecutive years.Formulating audit, focusing on 44 major severe affected counties, the main problems discovered: First, 9 counties and 1 provincial enterprise in Qixian County and 1 provincial enterprise of 405 million yuan in post -reconstruction funds are not compliant; Wei Hui and other 2The county financing platform company resumed RMB 30.918 million after the disaster was intercepted.

The second is that 162 projects in 24 cities and counties, including Boai, have been advancing slowly, involving a planned investment of 3.127 billion yuan; 4 cities and counties such as Huangchuan reported to 22 projects to start or completed, involving a planned investment of 12.83100 million yuan; Xinmi and other 4 cities and counties have reported 432 million yuan in investment in 15 projects.

Third, 24 cities and counties including Xinyang and including Xinyang were delivered and delivered for unattended collection, involving the investment completion of 563 million yuan; after the completion of 73 projects in 73 counties, including Zhengyang, the quality of the project was not up to the standard.In other issues, the planned investment amount was 3.346 billion yuan.Fourth, three counties including Junxian County, 3 counties, obtained 375 million yuan in reconstruction funds in violation of regulations.

The report quoted the website of the "July 20th" of the "July 20th" severe rainstorm disaster survey report released by the China Emergency Management Department on January 21 last year, from July 17 to 23, 2021, Henan Province was rare in history.The heavy rainstorm and severe floods occurred. The province disappeared 398 people in the province, of which 380 were in Zhengzhou. According to the inspection and evaluation, there were 150 counties (cities, districts) in Henan Province, with a disaster in Henan Province, with a direct economic loss of 120.06 billion yuan.Among them, Zhengzhou was 40.9 billion yuan, accounting for 34.1%of the province.

The Guangming.com of the China Official Media Guangming Daily published a comment on the content of the aforementioned report that the report revealed that in July 2021, Henan Province suffered a rare heavy rain in history.There are problems with the use of reconstruction funds.

The comment article questioned that the funding for post -disaster reconstruction was a special funds allocated by the state and the government. Why didn't they use the people?Who is so bold?Where is the supervision verification?

At the end of the article, there was a problem with the post -disaster reconstruction funds of the reconstruction of the homeland. It was the country that lost the country.The money of the country and the money of the people must be clear and must be checked at the end.